Approving or starting a Permit
Who is this article for?Users who want to learn how to approve or start a Permit.
Permit Approvers must validate Permits before approval.
Before any hazardous work can commence, it's imperative to obtain an approved Permit to Work through the proper channels. Carefully reviewing and approving a Permit to Work involves assessing risks, implementing control measures, and formally authorising the start of specific activities to ensure the safety of personnel and assets.
1. Approving a Permit
Video: Approve Permit
Before the permit can be approved, it must be validated by the permit approver. It can then be approved or rejected from the permit page:
-
Locate the specific permit using relevant filters.
-
Click the permit or Edit to the far right of the permit.
-
Review all details of the permit and scroll to the approval section.
- Enter any comments.
- Click Reject to reject the permit.
- In the pop-up window enter comments for the rejection.
- Click OK to save and to return to the Permits page.
- The Permit status will change to Draft until it is resubmitted.
- Click Approve to approve the permit and return to the Permits page.
- The permit status will change to Approved.
2. Start the Permit
Video: Start and Finish Permit
Once approved, the permit can be marked as started. All isolations must be marked as isolated (set to Yes) first.
To mark a permit as Started, from the Permit page:
- Locate the specific permit using relevant filters
- Click the permit or Edit to the far right of the permit
- Review all isolations and ensure all are marked as isolated set to Yes.
- Scroll to the start section.
- Click Start.
- Click Save or the Permits menu to return to the Permit page.
- The permit status will change to Started.